Parks Roads Reconstruction Project: Phase 2

What's New...

December 30, 2022:

Phase 2 of the Parks Road Reconstruction Project is in design with construction anticipated to start in Winter/Spring 2023.

Project Overview

Phase 2 of the Parks Roads Reconstruction Project, which is scheduled to break ground in the spring, includes the reconstruction an approximately 1.5-mile-long section of Garland Prairie Road from the BNSF railroad frontage area to just past the intersection with Pine Aire Access. This $2.4 million project also includes the reconstruction of the 700-foot paved section of Pine Aire Access. 

  • Status: In Design
  • Project Designer: Coconino County Public Works
  • Estimated Construction Start: Winter/Spring 2023
  • Estimated Construction Completion: Spring 2023
  • Estimated Project Cost: $2.1 Million
  • Project Contractor: TBD