Bellemont Access and Safety Improvements Project 

Bellemont Projects Slide Show

What’s New...

July 06, 2021: Phase B of the Bellemont Access and Safety Improvements Project continued on schedule last week with the contractor completing the first lift of asphalt paving on the west end of Shadow Mountain Drive and catch basin work on the east end of the project. Other work included installation of the light pole base at the intersection of Shadow Mountain Drive and Hughes Avenue. This week's work is scheduled to include installation of the light pole, excavation near the east end of Shadow Mountain Drive and grading in preparation for roundabout paving. 

Project Overview

The Bellemont Access and Safety Improvements Project will address traffic flow and safety issues at the intersection of Hughes Avenue, Shadow Mountain Drive and Brannigan Park Road in Bellemont.

Phase B

Phase B will include the construction of a roundabout and development of an alternative business access to improve traffic circulation for trucks, businesses, travelers and residents.

  • Status: Under Construction
  • Start: March 29, 2021
  • Est. Completion: Fall 2021
  • Project Engineer: Burgess & Niple, Inc.
  • Project Contractor: Banicki Construction
  • Est. Project Cost: $3,200,000

Phase 2 Culvert Installation Project

  • Status: Completion
  • Start: October 19 2020
  • Completion: November 19 2020
  • Project Engineer: Burgess & Niple, Inc.
  • Project Contractor: Banicki Construction

Public Works’ contractor has installed five corrugated metal pipe (CMP) culverts under Shadow Mountain Drive. This project, which was a prerequisite for Phase B of the upcoming Bellemont Access & Safety Improvements Project, was conducted this fall to provide a head start for Phase B of the Bellemont Access & Safety Improvements Project next spring. 

Earlier this year bedrock was encountered in the area near Shadow Mountain Drive by utility companies doing relocation work. Removal of the bedrock delayed completion of this utility relocation work, the result of which was a major factor in the decision to move the start date for Phase B from summer 2020 to spring 2021. Installing culverts this fall has helped to ensure that Phase B starts on time next spring as soon weather permits.

Phase A

Phase A of the project included a four-foot shoulder widening of Shadow Mountain Drive to install multimodal lanes between Alpine Road and Pegasus Drive.

  • Status: Completed
  • Start: May 18, 2020
  • Completion: July 27 2020
  • Project Engineer: Burgess & Niple, Inc.
  • Project Contractor: Banicki Construction
  • Project Cost: $555,577

Bellemont Cluster Box Unit (CBU) Mail Delivery Project

Project Overview

  • Status: Completed
  • Construction Start: April 22, 2020
  • Completion: May 8 2020
  • Project Contractor: Banicki Construction