Mountain Dell Projects

Mountain Dell Access Road Reconstruction Project

What's New...

April 2, 2021: On Tuesday Public Works met with the geotechnical engineering firm that will take and analyze roadway core samples to help determine design requirements for the Mountain Dell Access Road Reconstruction Project. Additional surveying work for the project has been completed and drainage improvements are being incorporated into the project. 

Project Overview

The Mountain Dell Access Road Reconstruction Project includes replacement of the old, cracked asphalt on Mountain Dell Access Road from just past the Beulah Blvd. transition area to the Mountain Dell subdivision. The currently paved sections Palmer Avenue and Sinclair Street in Mountain Dell also will be repaved as part of this project, which is expected to break ground in late spring or early this summer. 

  • Status: In Design 
  • Est. Construction Start: Spring 2021
  • Completion: Summer 2021
  • Project Contractor: TBD
  • Project Engineer: Coconino County
  • Construction Cost: TBD

Fort Tuthill Utility Improvement Project

What's New...

April 2, 2021: The contractor has completed installation of all but one sewer connection and is finished with all underground work. Upcoming punch list items include sewer line pressure testing and epoxy coating of manholes when temperatures permit. Trail restoration work is scheduled to start next week with demobilization expected by the end of the month.

Project Overview

The Fort Tuthill Utility Improvement Project will extend the sewer line from University Heights through Mountain Dell to Fort Tuthill to provide sewer service to the park. For more information please visit the project’s web page.

  • Status: Construction
  • Construction Start: July 2020
  • Estimated Completion: April 2021
  • Project Contractor: Overley’s Est. 1959
  • Project Engineer: Shephard-Westnitzer, Inc.
  • Estimated Construction Cost: $2,100,000 
  • Funded By: Coconino County Parks and Open Space Tax

Mountain Dell Drainage Improvement Project

What’s New...

October 02, 2020: Final change-order work for the Mountain Dell Drainage Improvement Project continued this week for channel signage and project as-builts. Final completion and sign-off for the project is expected next week. 

Project Overview

The Mountain Dell Drainage Improvement Project will improve the drainage in the community to accommodate a 100-year flood event. The goal of this project is to decrease the size of the flood-affected area. When completed, the project will provide flood mitigation for 28 structures, including approximately 20 homes and the community’s water system, which could positively impact flood insurance rates for these properties.  

  • Status: Completed
  • Construction Start: May 4, 2020
  • Completion: September 25, 2020
  • Project Contractor:Tiffany Construction Co.
  • Project Engineer: Civiltec Engineering, Inc.
  • Construction Cost: $2 Million
  • Funded By: Coconino County Flood Control District 

Mountain Dell Drainage Improvement Project Background

In 2016 the Coconino County Flood Control District (FCD) completed Initial Engineering Assessments (IEAs) in four areas of the County deemed "Special Flood Hazard Areas" by the Federal Emergency Management Agency (FEMA). An IEA is a tool that the FCD uses to better understand flood risks so that initial, conceptual flood mitigation alternatives can be identified and evaluated.

Based on this IEA information, the FCD Board of Directors approved preliminary engineering and feasibility studies for the conceptual Mountain Dell/Sinclair Wash Drainage Improvement Project.