Kiowa-Comanche County Improvement District

Summary Information

 Location:  Mountainaire
 Date Formed:  July 9, 2001 (Resolution 2001-53)
 District Engineer:  Shephard-Westnitzer, Inc., Flagstaff, AZ
 Bond Counsel:  Greenberg Traurig, LLP, Phoenix, AZ
 District Size:  Approximately 233 parcels
 Notes:  Typical section to consist of 4" asphalt millings with a chip seal. A scarcity of asphalt millings delayed the project from 2002 to 2004.
 Estimated Construction Cost:  $626,931.00
 Estimated County Contribution:  $358,514.00 (including drainage improvements)
 Estimated Total Project Cost to District:  $375,110.00
 Construction Hotline:  (866) 593-2877

Construction Updates

January 2006 - Project Complete.