Spring Valley Road Drainage Improvement Project

What's New...

June 14, 2019: This week concrete footers were poured in preparation for next week’s culvert pipe installation. The project remains on schedule for completion next month.

Project Overview

The Spring Valley Road Drainage Improvement Project is intended to help mitigate seasonal roadside drainage issues that occur near the intersection of North Spring Valley Road and Pumpkin Center Road. This project, which features the installation of a vented low-water crossing, went to construction this spring and is scheduled be completed this summer.

  • Project Status: Under Construction
  • Construction Start: May 22, 2019  
  • Estimated Construction Completion: June 30, 2019
  • Project Contractor: Rummel Construction, Inc.
  • Project Cost: $300,000

Construction Information

Rummel Construction, Inc. is scheduled to work from 6:00 a.m. through 4:00 p.m., Monday through Thursday with some weekend work possible. Detours will be in place and flaggers; signage and other traffic control will be used to guide vehicles through the construction zone. This project is slated to be completed this summer; however, this schedule is subject to change based on weather and other unforeseen factors.