Burris Lane Drainage & Road Improvement Project

What's New... 
   
07/27/2018: 
Work on the Burris Lane Drainage & Road Improvement Project continued this week despite rainy monsoon conditions. Crews focused on post-paving work, which included ditch grading and the installation of concrete water valve collars, road signs and survey markers. Roadway striping and shoulder hydro-seeding are scheduled for next week. The project remains ahead of schedule with substantial completion slated for next month. This schedule is subject to change based on weather and other unforeseen factors. 

Tiffany Construction Co. is working daily between 7:00 a.m. and 5:00 p.m., Monday through Friday with some weekend work possible. Flaggers, signage and other traffic control devices are in place as needed to direct vehicles through the construction zone.

March 14 Community Meeting Materials:

Meeting Presentation

Project Cross Section

Project Area Roll Plot

Project Overview

The Burris Lane Drainage & Road Improvement Project is necessary to improve and extend the service life of Burris Lane. Funded entirely by Prop. 403, this project includes utility relocation, localized drainage improvements, pavement rehabilitation and installation of widened shoulders for multimodal use.

Status: Under Construction
Construction Start: April 23, 2018
Est. Completion: Fall 2018 

Project Contractor: Tiffany Construction
Project Engineer: Kimley-Horn
Offsite Drainage Engineer: Civiltec Engineering Inc.

Est. Construction Cost: $2.4 Million