Townsend-Winona Road Pavement Repair Project

Construction Information

C and E Paving and Grading is scheduled to work daily between 6:00 a.m. and 4:00 p.m., Monday through Thursday with some Friday or weekend work possible. Flaggers, signage and other traffic control devices will be in place as needed to direct vehicles through the construction zone. Drivers should expect delays during construction. The project is expected to last approximately three weeks. This schedule is subject to change based on weather or other unforeseen factors.

Project Overview

The Townsend-Winona Road Pavement Repair Project is necessary to repair the deteriorated four-mile stretch of Townsend-Winona Road between U.S. Highway 89 to just east of Rio Rancho Road. This “mill and fill” project, which was approved by the Board of Supervisors on April 2, 2019, includes the milling of two inches of existing asphalt and the installation of approximately 2.5 inches of asphalt on the travel lanes and shoulders of Townsend-Winona Road between U.S. Highway 89 and just east of Rio Rancho Road. This section of roadway was severely impacted by freeze/thaw cycles that created numerous potholes along the roadway during the winter. Left unrepaired, the pavement would continue to deteriorate and require a complete and very costly reconstruction. 

  • Status: Under Construction
  • Estimated Construction Start: April 8, 2019
  • Estimated Completion: May 3, 2019
  • Project Contractor: C and E Paving and Grading
  • Estimated Construction Cost: $1.4 Million